Aldergrove Water Treatment Plant Tank Replacement

ClientTownship of Langley
LocationLangley, BC
Year2021
ConsultantAssociated Engineering

About the Project

11

This project will involve a 3-month shut down of the plant to facilitate the replacement of 2 creation tasks and 3 filtration tanks with 2 new Gravity filter tanks.

Scope of Work

– Demolition of 2 reaction tanks and 3 filtration tanks

– Installation of two new filter tanks

– Cleaning of reinforced concrete clearwell and backwash reservoir

– Removal, storage and reinstatement of existing filter