Anderson Creek Bridge

ClientCity of Surrey
LocationSurrey, BC
Year2019
ConsultantKlohn Crippen Berger

About the Project

11

Luxton Construction was awarded the Anderson Creek Bridge by the City of Surrey. The project started in August 2019 and was completed in November of 2019.

Scope of Work

– Bridge Demolition
– In-Stream Work
– Pile Driving
– Concrete Work
– Girder Erection
– Bridge Deck Concrete
– AC Paving
– Riparian Work
– Environmentally Sensitive
– Working under 500KV line
– Landscaping