CBSA Aldergrove Crossing Canopy Assessment and Repair

Aldergrove, BC

Project Info

The work comprised of the replacement of structural steel, soffit and parapet cladding and associated components following heavy damage to the Secondary Inspection Area (SIA) Canopy at the Aldergrove Port of Entry by a runaway asphalt milling machine that caused structural and aesthetic damage. The border crossing remained active over the entirety of the project. 

Point of representation between Canada and the United States. 

Scope of Work

  • Steel Erection
  • Steel Fabrication
  • Cast-in-Place Concrete
  • Electrical Works
  • Canopy Aesthetics Repair
  • AC Paving
  • Retaining Wall Construction
  • CONTRACT VALUE$350,000
  • CLIENT
  • CONSULTANTBoldwing Continuum
  • TIMELINEJanuary 2021 - April 2021